1. From the CMMS dashboard click Work Order Corrective. See Figure below.
Figure 1 : Work Order Corrective List
2. Check for date
from and to and click Add button. Date
from and to must be the range of the date the corrective maintenance schedule date, otherwise you cannot view the added entry. Then click Add button.
Figure 2 : Work Order Corrective List
3. Now all the textboxes and buttons that need entries will be enabled.
W.O. No.: the system will get the last available W.O. No. Fill up data especially W.O. No, Eq. ID, Sched. Date, and Date Reported.
Getting equipment ID, please click the button and select an equipment you would like to create a breakdown.
Figure 3 : Corrective Work Order List
4. Then click
Save button.
Figure 4 : Corrective Work Order List
5. Now a
Work Order has been created. Highlight the Work Order and click
Labor/Materials Needed tab.
Figure 5 : Corrective Work Order List
6. If in case there is/are material/s needed click
Add Material>> button. A vacant row will appear in the lower grid. Enter value in each column if needed.
Figure 6 : Materials
7. After entering values in every column and if there is a tax for every material cost click the Tax checkbox to check.
Figure 7 : Materials
8. Entering values in a cell and press enter or removing focus on the cell will save the data or you can click Save button. Next click
CM Task tab.
Figure 8 : Materials
9. Click
Add Task button. A popup of Corrective Libraries will appear.
Figure 9 : CM Task
10. Highlight a corrective maintenance task and click
SELECT button or you can double click mouse. Note, if you cannot find one you can just select one and edit it. If you want it to appear in the popup add it in the setup of Corrective Maintenance Libraries.
Figure 10 : CM Task
11. You can still edit the Task Description. Complete the entries.
Figure 11 : CM Task
12. Enter
Remark if any abnormality only column.
Figure 12 : CM Task
13. Now click
Image tab.
Figure 13 : CM Task
14. Click
1.Upload Image Before button.
Figure 14 : Image
15. Click
Browse button.
Figure 15 : Image
16. Locate and select image and click
Open button.
Figure 16 : Image
17. Then click
Submit Picture button.
Figure 17 : Image
18. Again click
2.Upload Image Before button. Two images needed in the breakdown report. Image Before is needed in breakdown report. The Image After is for accomplishment report.
Figure 18 : Image
19. Click
Browse button.
Figure 19 : Image
20. Locate and select image and click
Open button. Then click
Submit Picture button. Same procedure for Image 1.
Figure 20 : Image
21. Image 1 and Image 2 has been uploaded.
Figure 21 : Image
22. In the
Print pulldown menu click
WO-Breakdown Report.
Figure 22 : Breakdown Report
22. Click
Print Work Order button.
Figure 23 : Breakdown Report
22. Print Breakdown Report.
Figure 24 : Breakdown Report
Note : Be sure to fill up in (Figure 3 : Corrective Work Order List) the Customer Complaint, Cause of Trouble and Recommendation.